High cost, corruption claims mar Brazil World Cup
BRASILIA, Brazil— The cost of building Brasilia’s World Cup stadium has nearly tripled to $900 million in public funds, largely due to allegedly fraudulent billing, government auditors say. The spike in costs has made it the world’s second-most expensive soccer arena, even though the city has no major professional team.
Mane Garrincha stadium, which boasts 288 imposing concrete pillars holding aloft a high-tech self-cleaning roof, has become the costliest project related to Brazil’s $11.5 billion World Cup. Critics call it the poster child for out-of-control spending and mismanagement, or worse.
Article continues after this advertisementNow, an Associated Press analysis of data from Brazil’s top electoral court shows skyrocketing campaign contributions by the very companies involved in the most Cup projects. The lead builder of Brasilia’s stadium increased its political donations 500-fold in the most recent election.
The financial links between construction firms and politicians add to deep suspicions among Brazilians that preparations for soccer’s premier event beginning next month are tainted by corruption, raising questions about how politicians who benefit from construction firms’ largesse can be effective watchdogs over billion-dollar World Cup contracts. Anger over perceived corruption helped fuel huge protests last year, and there are fears more unrest could mar the Cup.
“These donations are making corruption in this country even worse and making it increasingly difficult to fight,” said Renato Rainha, an arbiter at Brasilia’s Audit Court, which is investigating the spending on Brasilia’s stadium. “These politicians are working for those who financed campaigns.”
Article continues after this advertisementIn a 140-page report on the stadium, the auditors found $275 million in alleged price-gouging — and they have only examined three-fourths of the project. They forecast that fully one-third of the stadium’s cost may be attributable to overpricing, the largest single chunk of $500 million in suspect spending auditors have flagged in World Cup construction projects so far.
Federal prosecutors say as yet no individuals or companies face corruption charges related to World Cup work, but it could take years for official audits to be finalized and judged by civil courts, a required step before any criminal charges are filed. There are at least a dozen separate federal investigations into World Cup spending.
“Is there corruption in the Cup? Of course, without a doubt,” said Gil Castelo Branco, founder of the watchdog group Contas Abertas that campaigns for transparency in government spending. “Corruption goes where the money is, and in Brazil today, the big money is tied up in the Cup.”